ENGIE Brasil Energia S.A.

Greenhouse gas emissions & sustainability report data

📊 Latest report period: 2023-04-01 to 2023-06-30🗂️ Report periods on file: 2023-04-01 to 2023-06-30, 2022, 2019

In its 2023-04-01 to 2023-06-30 reporting, ENGIE Brasil Energia S.A. disclosed greenhouse gas emissions of 9.8K tCO2e (2Q23); 209695 tCO2e (6M23). Figures are as stated in the company's own report and may use different boundaries, units or methods (for example market-based vs location-based Scope 2), so compare with care.

💨
GHG Emissions
9.8K tCO2e (2Q23); 209695 tCO2e (6M23)
2023-04-01 to 2023-06-30
⚡
Renewable Energy
100.0% (2Q23); 100.0% (6M23)
of total energy
💧
Water Usage
919 megaliters (2Q23); 1,418 megaliters (6M23)
2023-04-01 to 2023-06-30

📈 Emissions by Report Period

Report periodHeadline emissions figure reported
2023-04-01 to 2023-06-309.8K tCO2e (2Q23); 209695 tCO2e (6M23)
20221.1M tCO2e/year (operating control)
20195.3M tCO2e (operational control) and 5293110 tCO2e (equity share)

Each row is the headline figure extracted from a different report; scope coverage and methodology can change between years.

✅ Reported Environmental Achievements

🎯 Climate & Sustainability Targets

🔜 Short-term

  • Reduce emissions intensity (Scopes 1, 2, and 3) by 30% by 2025.

📅 Medium-term

  • Reduce emissions intensity (Scopes 1, 2, and 3) by 56% by 2030.
  • Have 100% of assets covered by climate adaptation plans by 2030.
  • Engage 100% of top Scope 3 suppliers to set science-based targets by 2030.

🔭 Long-term

  • Emissions neutrality by 2045 (aligned with ENGIE Group's commitment).

🌱 ESG Focus Areas

Climate ChangeRenewable EnergySupply Chain SustainabilityCommunity EngagementEmployee Well-beingCorporate Governance

⚠️ Challenges & Risks +

  • Reduction in energy sales volume due to lower sales volume available to free consumers and reduction in sales volume to distributors.
  • Decreased uptime of certain Wind Complexes due to problems with frequency converters and wind turbine blades.
  • Transmission constraints imposed on plants of the Madeira Complex, preventing them from operating at full capacity.
  • Lower generation at Jirau HPP due to favorable energy scenario and large supply on the National Interconnected System.

📋 Report Information

Reporting Period: 2023-04-01 to 2023-06-30
Frameworks: GRI, SASB, IIRC