- Lingering effects of the COVID-19 pandemic continue to impede workforce maintenance and progress on NSMVs, contributing to schedule impacts, productivity loss, and increased costs.
- COVID-19 pandemic and federal contractor vaccine mandate prevented workforce ramp-up according to plan.
- Increased costs of labor, turnkey suppliers, and overhead driven by schedule delays and compression.
- SRIV project is now a loss-making contract.
- NSMV series is a loss-making contract (although more loss has been recognized than anticipated upon completion).
Philly Shipyard ASA
Greenhouse gas emissions & sustainability report data
Figures are as stated in the company's own report and may use different boundaries, units or methods (for example market-based vs location-based Scope 2), so compare with care.
📈 Emissions by Report Period
| Report period | Headline emissions figure reported |
|---|---|
| 2023 | 13.6K MT CO2e |
Each row is the headline figure extracted from a different report; scope coverage and methodology can change between years.
🌱 ESG Focus Areas
SafetySustainabilityEnvironmental, Social, and Governance (ESG)